Construction Diary

How fast can a HANSE HAUS be built?...

Day 1 / 05.30am
The basement slab or traditional foundation is made ready to receive the house.

Day 1 / 06.00am
The first wall panel is set in position and securely anchored to the basement slab.

Day 1 / 10.00am
The ground floor is built quickly and easily. Next, laying the thermal insulation and sound proofing for the first floor begins.

Day 1 / 12.00noon
Internal stairs, made in the factory and carefully packed, are installed.

Day 1/ 06.00pm
The pre-fabricated roof elements are fixed down in preparation for roofing.

Day 2 / 07.00am
On the second day, the roof goes on.

Day 2 / 04.00pm
The roof is in place and the house is protected from the elements.

Weeks 2-4
Inside, fitting out begins with the installation of sanitary ware…

Week 5
Installation of sanitary ware has been finished...

Week 6
...and the furnitures is set in place by the owners.

After a 6 week construction period the house is handed over to its proud new owners.